|
Index
> LATEST
• 2012
• 2011
• 2010
• 2009
• 2008
• 2008 (Phase One)
NOTE: Most images on this page will enlarge if
you click on them.
Sunday Afternoon 13th December 2009
Chris Batstone, Jeff Price, Tony audsley.
Took bags of rock from Caine Hill and packed them round the
top of the shaft to fill the voids there.
Sometime in November 2009
Chris Batstone, Jeff Price, Tony Audsley.
Moved the little digging hut towards the centre of the
depression to make space for a new digging hut cum engine house.
Started laying down a foundation of rock (from Caine Hill)
for the new hut.
Wednesday Evening, 28th October
2009.
Jeff Price, Paul Brock, Tony
Audsley.
Tried out silly idea No. 542, which was to blast a dry mix of
3:1 sand:cement using compressed air. The idea being to
fill the gaps in the spoil with sand/cement, which would the
absorb moisture and harden. ; This worked moderately well,
but it also filled the shaft with an unbreathable cloud of cement
dust. Lacking any form of respirator or dust filter, the
attempt was abandoned in favour of sloshing in a wet mix.
No spoil removed.
Monday Afternoon 26th October 2009
Alice Audsley, Annie Galloway, Roger Galloway,
Tony Audsley.
The depression was dry, although the new blue drain pipes were
taking a very small amount of water. There was a small
pool at the bottom of the shaft.
Tried drilling into the rock walls, with slightly mixed
sucess. Got three good holes in but when trying to work to
the left or the right of these found that solid rock was more
that a drill length away. Hauled out two of the bags of
fill put down there on 18th July; three more to go.
Also hauled out one load of 'proper' spoil.
Wednesday 30th September 2009:
Ivan Sandford, Jeff Price, Tim Large, Tony
Audsley
Some time ago, Tim had bought a 15 ft long, substantial
section I beam from a lady in Blagdon. There may well be a
fascinating story attached to this, but I know of no other
details.
The removal team hauled it out and loaded it onto Ivan's
trailer, drove in convoy to Home Close and deposited it with the
rest of the ironwork at t'hole.
Then retired to Hunters' for tea and biscuits.
Wednesday 12th August 2009:
Jeff Price, Tim Large, Tony Audsley
Surface preparation work. Dug channels to the
drainage sump and filled them with the Belfry gravel. Rain
prevented further play, so we retired to Hunters'
(Sensible decision).
Monday 10th August 2009:
|
Took 12 bags of ½" stone from the Belfry car-park
to t'hole (thank you to Henry Dawson for this). The
depression drainage system seems to be working well and the
ground around the yellow sump is drying out and beginning to
crack.
For those of you who feel tired, jaded and sad, here is an
exciting photograph of mud ... drying ... slowly ...
|

10AUG09: Cracks in the drying mud.
|
Wednesday, 5th August, 2009:
A quick visit to check if the drainage system was working
after the torrential day of rain on Tuesday. The
depression was draining well and a small amount of water was
still running down the pipes. By contrast, the adjacent
depression had a 16 inch (or 406mm if you insist) deep pool.

05AUG09: The drained, but still soggy,
depression. |

05AUG09: The drainage sump (a yellow plastic
bucket). |
05AUG09: For comparison, the undrained next
depression with a 16 inch deep pool at the bottom. |
Sunday, 2nd August 2009:
Alice Audsley, Annie Audsley, Roger Galloway, Tony
Audsley.
Another day of surface preparation. The intention was
to stop the water from the pool flowing down the outside of the
shaft as this was washing away material from around the concrete
rings. The theory was that if the water were piped to the
shaft bottom the spoil round the bottom ring of the shaft would
dry out a bit and be more amenable to being under-mined.
So, we started by digging a trench at the level of the bottom
of the first ring from the shaft towards the centre of the
depression. Roger then drilled a couple of 60mm holes
through the ring and a couple of pipes were run from the bottom
of the shaft through the holes and along the trench to a bucket
which had been sunk in the slime in the centre of the depression.
Much fun was had by all.
More importantly, the pipes seemed very effective at draining
the depression. We'll see what happens next time it
rains.

Alice Audsley, Annie Audsley & Roger
Galloway digging a trench for the drainage pipes |

Roger Galloway trimming a hole he has just
drilled |

The drainage pipes fitted in the shaft
|
Saturday, 18th July 2009:
Chris Batstone, Stuart Lindsey, Tony Audsley
Started off with the intention of filling the hole that Paul
had dug out on Wednesday with some bags of spoil to prevent any
risk of a run-in.
Unfortunately, the fill had beaten us to it and wiped out
Paul's work very neatly. Four out of the five ree-bar
supports had held, but mud had sludged between the bars and rocks
had moved down from the right-hand (western), unsupported side of
the excavation.
Hole 1, Diggers 0.
A reverse digging session then started. Five bags of
spoil were lowered down the shaft and jammed in, round and under
to prevent further collapse.
Back on the surface for pies and bread pudding, provided by
Stuart. This was followed by a silly afternoon session,
nominally with the purpose of draining the pond with the eventual
intention of piping the water down the inside of the shaft.
In reality, I guess that we just liked playing in the
mud.
Digging total:- minus 5 bags of spoil removed from the
dig.
Friday Afternoon 17th July 2009:
An afternoon of steady, heavy rain. Went over to
t'hole, filled the watertanks in preparation for cementing at
the weekend and generally fiddled about on the surface while they
were filling.
The pond had overflowed the dam of spoil and a respectable
stream of water was flowing down the shaft.
The site looks much too wet to attempt cementing at the
weekend.
Wednesday Evening, 15th July 2009:
Henry Dawson, Jeff Price, John Noble, Paul Brock,
Tony Audsley.
Digging down below the temporary roof of reebars in
preparation for casting the first cement seating for the shaft.
Paul did most of the digging and John did most of the
hauling. Nine loads, one rock and one frog were hauled up
the shaft. Strictly speaking, the frog travelled up the
shaft inside John's oversuit; when he got to the surface, it
took quite a while to get the frog out as it seemed to have
formed a strong emotional attachment to John.
Later Henry and Tony went down to test the washing system.
At first this insisted on producing only a pathetic
dribble despite much pipe blowing and sucking by the surface and
underground teams. Finally, the joint between the
down-pipe and the tap was opened and the tap and the bottom 6
inches of pipe were found to be stuffed with small leaf
fragments; a leafcutter bee had made a nest in the hose pipe.
Once this blockage was removed water sprayed everywhere.
Henry was OK, he was part way up the ladder.
Sunday, 12th July 2009:
Fixed up a header tank and connected it to the "water
main" in the shaft. Away from the dig, made up a skip
for lowering cement down the shaft.
Monday Morning, 6th July 2009:
Installed a water-pipe down the shaft with a tap at the
bottom. The water supply will come from a header tank on
the surface. This should be useful when the rock
wall needs cleaning up before casting the cement plug against
it.
Fitted a guide rope for the bucket to (hopefully) prevent it
from jamming against the ladder, which it seems to like to do.
After Hunters', dragged varied bits of scrap metal
from the heap at the dairy unit over to t'hole. Got
wet.
Friday Afternoon, 3rd July 2009:
Alice Audsley, Tony Audsley.
Had previously made up three more "drilling jigs"
and pointed up some lengths of ree-bar, so went down t'hole
and fitted the jigs to the bottom of the pipes then hammered the
pointed bars through the fill and into the wall behind. We
hope that just hammering the bars into position will work rather
than having to drill a hole for each bar ... time will tell.
When the bars were in position, excavated under them and
tunnelled towards the wall. Got to touch the rock wall!
As too much excitement is bad for the elderly, we packed
up at this stage. Nine (smallish) loads of spoil
removed.
Sunday Afternoon, 14th June 2009:
Alice Audsley, Chris Batstone, Tim Large, Tony
Audsley.
Found that the ladder anchors were firmly set, so bolted the
ladder to the wall. This is a great improvement as the
ladder no longer flails about at the bottom of the shaft.
The surface party (AA, CB, TL) then made a wall of
"sand" bags to prevent the heap of chippings from
sliding into the pond. The remnant of the team went down
the shaft and started drilling in the right direction to find the
rock wall. Drilling into the mudstone was a bit
problematical, as the relatively soft rock produced small chips
which repeatedly jammed the drill in the guide.
By the end of the afternoon, a fine retaining wall had been
built round the heap of chippings and two deep holes had been
drilled into the rock wall - more to follow.
Thursday Afternoon, 11th June 2009:
Jeff Price, Tony Audsley.
Jeff brought out his Hilti drill and a pukka Hilti resin kit
and resined some anchors in position for the ladder.
Sunday 7th June 2009
Started to shovel and barrow the aggregate into the
depression. A pathetically small amount was shifted in
this way then Pete Page turned up with his shovel and he shifted
the rest in less than 20 minutes.
Thursday 4th June 2009
Took delivery of 10 tons of aggregate and filled a 220 litre
container with water in preparation for cementing works at the
bottom of the shaft.
(Most of) May 2009
Most work involved
collecting "stuff" and fettling of winches and
generators for later use. At the dig, the old gate from
Fernhill cave was fitted to the top of the shaft.
Sunday, 26th April 2009:
Jeff Price, Tony Audsley.
Took generator and drill, cables etc over to the hole.
We found that the resin used to fix the ladder bolts to the pipes
had not hardened. Either it had not mixed properly, or
more likely, too old. Jeff Will get some new resin.
Tony used the drill jig and 1 metre drill bit to drill into the
rock under what he thought was the north wall of the shaft; only
to find that all four holes attempted went to full depth without
hitting much that was solid. Much confusion as the rock
wall of the rift was known to be less than two feet away.
After much scratching of head and looking at it from the top
and the bottom of the shaft, it appears that he had been trying
to drill ALONG the rift rather than into the wall, ie east
instead of north, 90° out. Never mind, better luck
next time.
Wednesday Evening, 22nd April 2009:
Jeff Price, Tim Large, Tony Audsley.
Fitted small brackets to the bottom of the two ladder
standoffs, then drilled 8mm holes (about 2 inches deep) in the
concrete pipes, filled with resin and inserted stainless studding
to anchor the ladder. This left to harden until next visit
before bolting together.
Probed under the north wall to try to find the
"solid" rock wall of the rift which is behind there
somewhere. Either we didn't find it or it is not very
solid; more work required. Then used Jeff's 36 volt
Hilti to drill about 14 holes in a line across the boulder in the
floor and used a gad (spike) in the holes to split the rock in
two. Removed 1½ skip loads, mostly shattered
rock.
Monday Morning, 20th April 2009:
Alice Audsley, Tony Audsley.

|
Went over and took some photographs of the bottom of the
shaft, detailing the jacks and strapping.
|
|
Sunday Morning, 19th April 2009:
Duncan Butler, Jeff Price, Tim Large, Tony
Audsley.
Tony fitted the now newly freed bottle-jack, then dug out 9
skip loads. Duncan then came down and dug out a further 6.
There is a large(ish) boulder appearing at the bottom of
the shaft which will have to be removed before too long.
Wednesday Evening, 15th April 2009:
Jeff Price, Tim Large, Tony Audsley.
Excavating at the bottom of the shaft for fitting the straps.
Fitted the second strap and jack and fixed the third strap
into position, but then found that the third jack was jammed
solid, so couldn't fit it. Ten skip loads removed.
Took the jammed jack away for fettling.
Monday Morning 13th April 2009:
Jeff Price, Tim Large, Tony Audsley.
Excavated at the base of the shaft to try to fit the bottom
straps and jacks. Managed to fit one. Ten skip
loads removed.
Friday, 3rd April 2009:
Alice Audsley, Tony Audsley.
|
A day largely of surface work; started at home, welding on
strips to reinforce the bottom hooks. Then took all back
to Wigmore and tried the jacks and lower straps in position in
the shaft, measuring up for the bottom loops. Then to
Nigel's workshop with the marked-up bottom straps and used
some more of his gas (many thanks) to heat and form the loops for
the bottom straps.
|
|
Thursday 2nd April 2009:
Continued working in Nigel's workshop. Reinforced
the top hooks by welding on strips to form a channel section.
Ground down the loops to fit the top of the jacks, then
towed the top straps back to the dig and lowered them down the
shaft and fitted roughly into position.
Wednesday, 1st April 2009:
Towed the three 10 metre steel straps from the shaft to Nigel
Perkin's workshop. Then used his gas set to heat and
bend the straps to form hooks to fit over the ends of the shaft
and loops to connect to the jacks.
A few notes
- 2009 (012) Tue, 31st Mar: More work on the jacks -
all day.
- 2009 (011) Sun, 29th Mar: All day working on
freeing the screw jacks.
- 2009 (010) Sat, 28th Mar: Working in Nigel
Perkins' workshop bending the ends of the short (bottom)
straps to fit the shaft and the jacks.
- 2009 (008) Fri, 20th Mar: All day on the bottle
jacks.
- 2009 (007) Thu, 19th Mar: All day working on the
bottle jacks.
- 2009 (006) Sun, 15th Mar: Visited and found voids
at the side of the shaft where the fill had been washed out.
Backfilled these with the stone from Caine Hill.
Took lengths of re-bar (which had been left at the Farm House by
Avon Steel) over to the dig.
- 2009 (005) Sat, 7th Mar: Working at home, freeing
rusted 5 ton bottle jacks obtained from the Belfry.
- 2009 (004) Mon, 23rd Feb: Took a few more Caine
Hill bags of stone over to the shaft.
- 2009 (001) Sun, 25th Jan: Took a few bags of stone
from Caine Hill over to the shaft.

15MAR09:Collapse by the side of the
shaft |

31MAR09: Applying heat and leverage to the
rusted jacks |

02APR09: Heating and hammering the straps to
hook the ends |

08APR09: The completed assembly of jacks and
bottom straps. |
Beginning of 2009 - Overview
2009 started still with no solution to the problem of holding
the shaft rings together. Steel strapping (50 x 6 mm flat)
had been at the dig since October, but no easy way of using this
to tension the column had presented itself. Some 5 tonne
screw-jacks had been noted half buried behind the Belfry, but
they were rusted solid and as the threads were 3½ in
diameter (38mm), I had discounted them thinking that they might
be impossible to free.
However, there was nothing else available; so a combination of
bloody-mindedness, a chain-wrench with a 6ft waterpipe extension
on the handle, a LOT of heat and a tiny bit of oil meant that
they gave way, a bit at a time. The most resistant took 12
hours, spread over two days, before both threads were free.
Top of Page
Created: 05-May-2010
|