Started cutting up a bed frame for the door framework then
realised that I did not have enough bed frame angle to complete the
job, so took the cut lengths over to the dig and measured again and
again (and again). Grabbed an extra length of angle iron and
a couple of lengths of decking timber from the hut and took it all
back to Cheddar.
Welded up the framework and cut some of the decking timber for
the doors. Set up the door assembly ready to weld the hinges
to the frame, at which point heavy rain stopped further play.
Saturday afternoon - PS: But, later on the sun
came out so, seizing the moment with both hands, the hinges were
welded to the frame. Four welds per hinge, all done in the
twinkling of an eye. The decking now needs bolting to the
hinges, with some bits of psychological reinforcement tacked on
underneath.
Sunshine - Hooray !!
2010 (164-170) ~ Sat 9th - Fri
15th Oct
Tony Audsley
All week fighting with mixer engines. Finally gave up on
the Honda and started work on a Briggs and Stratton.
2010 (162) ~ Thu 7th Oct (1330-1800)
Mike Wilson, Frank Hewlett, Tony Audsley.
Mike Wilson fixing the mixer engine at the
Belfry watched by (a beheaded) Frank Hewlett in the
background.
Collected the cement mixer body from Home Close, then to Uphills
to buy four BIG gate hinges for the shaft doors. Took all
this to the Belfry and met up with Mike Wilson who had the 'new'
replacement engine that he had bought on eBay. The intention
was to pop it on, start it up and then live happily ever after.
Unfortunately, these things are never quite that simple.
The replacement engine was an earlier type and the mountings and
drive did not quite match up. Three attempts and much filing
of slots, general bodgery and the uttering of magic words got us
somewhere near a working system, but heavy rain reduced the fun
element of the exercise, so we packed up and Tony took the mixer
back to Cheddar to continue playing with it.
Mike is getting a new piston and ring set for the old engine so
that we will have a spare, just in case.
2010 (157) ~ Thu 30th Sep (1400-1630)
Les Oxborough and Tony Audsley.
Finished bolting the ladder to the shaft and cut off the excess
studding. Then cut off all the metal steps which were cast
into the bottom pipe as the bucket was likely to catch on them.
2010 (155) ~ Mon 27th Sep (Various people
at various times between 1000 - 1640)
Tony Audsley, Mike Wilson, Les Oxborough.
Tony went over early to remove the engine from the cement mixer
with the intention of taking it to Mike Wilson at the Belfry.
The removal took much longer than expected. Packed
engine into the Land Rover and set off for the Belfry but met Mike
on the farm track coming to see what was taking so long. We
both went back to the dig where we engaged in long, involved and
erudite discussions until it was time for Hunters.
In the afternoon Les came out on his own and fixed galvanised
plates over the exhaust pipe hole in the hut and also a cowl plate
to keep rain off the silencer.
2010 (154) ~ Sun 26th Sep (1030-1645,
with a break at Hunters')
Tony Audsley, joined in the afternoon by Alice
Audsley.
Fitted J-Rat's original 6mm hauling cable to the winch and
looped and thimbled the shaft end of this. Then tried a
dummy run lowering the bucket to the shaft bottom and hauling it
out again!
In the afternoon repeated the process, this time after filling
the bucket with rocks. Hauling was OK but it was difficult
to achieve a smooth lowering on the brake. Perhaps it will
improve with practice. It is also a little difficult to hook
on the traverse chain without diving headfirst down the shaft.
May need to fit doors to the top of the shaft.
2010 (153) ~ Sat 25th Sep (1100-1645)
Tony Audsley, joined in the afternoon by Les
Oxborough.
Spent an hour in the hut checking over the engine and winch and
tightening all the nuts and bolts that had been forgotten.
Fitted the traverse pole and A-frame support to the headframe.
Remade the wire bracing on the north side of the headframe
(this had been a temporary bodge previously). Found that the
drainage sump was full of water to within ¼ inch of the outlet pipe
so we seem to have cured the leak for the time being at least.
Les started work on the metalwork to seal the hole where the
engine exhaust comes out of the hut.
2010 (151) ~ Mon 20th Sep (1030-1600)
Les Oxborough, Tony Audsley.
Installed the winch engine, cut a hole in the north wall of the
hut for the engine exhaust. Cut a hole in the west wall to
take a scaff pole connecting the winch to the headframe. Rearanged
the headframe to allow the bucket to travel further up into the
frame. (The traverse pole was in the way previously).
Sat on the wall, nattered and enjoyed the sunshine.
2010 (150) ~ Sun 19th Sep
Jeff Price, Phil Romford, Tony Audsley.
Jeff fettling the tipping bucket
Fitted more wire cross bracing to the headframe and set up a
scaffolding traverse and 'A' frame to ease handling of the bucket
at the top of the shaft.
2010 (149) ~ Sat 18th Sep (1130-1630)
Alice Audsley, Les Oxborough & Tony Audsley
The head frame with bracing
Back from holiday, but a slow start with quite a lot of faffing
attempting to fix a leak in the drainage sediment trap. This
involved drying out the chamber with a blowlamp then tipping in
molten bitumen and coating everything liberally with polyvinyl
acetate emulsion.
In the afternoon, fixed bracing scaffs from the base of the hut
to the top of the headframe and completed the resining of the bolts
for the fixed ladder (I think so anyway).
2010 (148) ~ Thu 2nd Sep (1220-1400)
Alice & Tony Audsley
A quick trip over to try to fix resin anchors for the new ladder
position. Not 100% successful. Drilled and cleaned
four holes and fixed the lowest anchor, but then had a faffing
episode during which time the resin set in the only nozzle that we
had with us, so the other three did not get done. Better
luck next time.
2010 (147) ~ Sun 29th Aug
Alice Audsley, Chris Batstone, Sam Batstone, Tony
Audsley
In the morning, realigned the winch and cut a hole in the wall
of the hut for the winch cable, then put up a shelf along the back
(east) wall in a possibly vain attempt to reduce the level of
clutter.
In the afternoon realigned the ladder in the shaft, tightened up
all the bolts on the headframe and finally removed all the
remaining stub brackets from the top of the yellow grill which had
made a nuisance of themselves when we were laying planks on the
grill. They are no more.
2010 (146) ~ Sat 28th Aug (1100-1730)
Alice Audsley, Les Oxborough, Stu Lindsay, Tony
Audsley.
Fitted the wire cross-bracing to the north side of the shaft,
this is not perfect but it will do for now. Introduced the
winch to the hut and built a scaffolding base for it. Stu
stacked gravel behind the wall to aid drainage.
Alice Audsley, Ian Gregory, Jeff Price, Mike Wheadon,
Phil Romford & Tony Audsley.
A short afternoon session after Hunters. Phil worked on the
headframe fitting two north south scaffs and then the sheave wheel
on top while the rest of us sat around and put the world to rights.
All in all a particularly fruitful afternoons work.
Went over to the dig and cut two of the long (6.42m) scaff bars
in half, thus making the four legs for the head frame.
Fitted these into position then set up a wooden working platform on
top of the yellow grill and fitted two top scaff bars (running
east-west). Then fitted one temporary north-south scaff and
tensioned wire cross bracings on the east and south sides of the
head frame.
At this stage, we needed another eight cable clamps to complete
the bracing but there was none left because he who bought them from
Uphills last Friday could not count. So we packed up and
went home - it was raining anyway.
2010 (137-140) ~ Mon 9th -
Sat14th Aug (on and off)
Making up a tipping skip. Because the steel strip was
thinner than I would have liked, welded two together back to back.
Lots of drilling, filing, grinding and welding.
The problem with the mixer turned out to be a heavily oiled
plug, so a quick wash and brush-up and it was as right as it will
ever be. Well, at least it started and kept running.
Mixed one load of mortar; extended the first course of
block-work and made a start on the second course.
Took some blocks away to cut them into artistic tapering
shapes.
2010 (134) ~ Mon 2nd Aug (am)
Tony Audsley.
Set up for more blockwork. Measured out sand and cement.
Set up the mixer; couldn't start it. Tried for about
30 minutes then gave up. Plenty of petrol but didn't have a
plug spanner, so could not check the spark. Try again
tomorrow.
Mixed one load of mortar. Filled the stub foundation
scaffold 'feet' with mortar to prevent ingress of water and future
rustage, rottage and general collapsery. Then started on the
first course of blockwork. Scattered a few drain holes artistically
about in the blockwork.
Noted that water poured anywhere on the patio area ran neatly
along the central channel and plopped down the drain; all very
satisfactory, (if not a little surprising).
2010 (132) ~ Thu 29th Jul:
(1030-1645)
Tony Audsley.
Spent all day melting bitumen over Slug's stove (sorry Slug, I
will clean it) and then filling the expansion joints. Very
slow, very tedious, very messy and occasionally painful (put
fingers in pool of bitumen).
2010 (131) ~ Wed 28th Jul: (pm)
Les Oxborough, {AA & TA}
Les went over to the dig and did an end-of-contract tidy up of
the site and removed his tools. He left his boots in the
hut, so hopefully he intends to return.
Alice and Tony went to Seymour Roofing in Weston and bought a
keg of bitumen to fill the expansion joints. Make a ladle out of
pop rivets, steel strip and a sweetcorn tin - fascinating.
Alice & Tony bought two bags of cement then went out to the
hole. Set up the mixer and then were joined by Les and Ian.
The last two panels of the patio were completed, 11 mixer
loads of concrete. The mixer was struggling, but made it
through to the end. One extra person makes all the
difference to the work-load, it was almost a pleasure.
After lunch at Hunters, Tony started work on a scaff framework
for the winch and got the basic outline completed, cross bracing
and suchlike still to do.
Tony and Alice went to the dig via Maunders to buy three bags of
cement. Arrived at the hole at 0930 and set up the mixer
ready for use. Les arrived at 1000 as agreed and we waited
about 15 minutes before starting as the weather looked rather
uncertain.
It did seem to be clearing so we started on the concreting.
Les laying the concrete, Alice measuring out cement and
aggregate and Tony carrying buckets, mixing and barrowing.
The first sector took four mixer loads and the second took nine and
a half. Towards the end of the second batch of mixing the
mixer showed serious signs of distress and it only just managed the
final mix.
Ate sandwiches at the site then left, taking the mixer back to
Cheddar to see if it could be fixed.
(The first attempt at fixing the mixer was not notably
successful, will try again tomorrow).
On Tuesday and Wednesday the Met Office forecast heavy rain so
there was no work at the dig (and also no heavy rain). So
today we ignored the weather forecast, which was for heavy rain
again and wrong again; at least they are consistent.
We had an early start and mixed and poured the first sector,
which took about two hours and was fairly straightforward. Finished
at 1200, then had some lunch and left the site at 1230.
We have decided on the term 'patio' as a name for the concreted
area round the shaft, for two reasons
With any luck it will wind up Trevor Hughes.
It is a perfectly respectable mining term - see extract from
Vol II of the Shorter Oxford (Marl to Z and Addenda)
2010 (124) ~ Mon 19th Jul:
Variously: Jeff Price, Les Oxborough, Tony
Audsley.
(AM) Jeff bought 20 concrete blocks and took them over to Home
Close, then went to Hunters'.
(AM) Tony worked at home preparing modified scaffold clamps for
cable bracing of the head frame, then went to Hunters'.
(PM) Les went over to Home Close and continued with his
preparations for the concreting.
2010 (123) ~ Sun 18th Jul:
(1000-1300)
Tony Audsley.
Tony went over in light but persistent rain. Started by putting
in some reinforcing bolts in the south wall of the hut where one of
the timber panels had started to bulge.
When the rain slackened, checked the alignment of the hut and
safety grill, because I didn't quite believe the laser level
results from Friday. It's not perfect, but within ½ inch or
so.
Then went over the positioning of the feet of the head frame,
setting them for position and depth and tightening all clamps.
Dug out some more from below them so they will be held by a
decent mass of concrete.
Les went over to the hole in the afternoon and prepared the area
for concreting the first segment (south-east).
Beware!, THE DAY
approaches!
2010 (121) ~ Fri 16th Jul:
(0900-1545)
Alice & Tony Audsley.
I think the time has come for a little bit of explanation about
what is going on.
The plan we have been working towards has been to create a
concreted working area around the shaft. This concrete pad
and its associated pipework would have a secondary function of
diverting water draining from the field away from the shaft and
into the sump at the centre of the depression.
The shaft is intended to have a 3 metre (ish) high head frame
consisting of four vertical scaffold bars fixed outside the
concrete ring and braced back by two longer bars running from the
headgear back towards the base of the hut. This is the
essence, there are all sorts of fripperies and minor irritations
still to be attached. The completed head frame should
resemble, by some quirk of parallel development, a miniature
version of the head frame at Magpie Mine (Derbyshire).
So much for the plan, reality is much slower. The day
started with Tony welding reinforcing pieces to the stub
foundations mentioned yesterday. Then went off to the hole
and an attempt to align the yellow cage, (an integral part of the
scaffold head frame), with the axis of the hut using a laser level
screwed to the side of the hut and bits of white hardboard and
rulers and suchlike.
Unfortunately, small brackets which had been left on the bottom
of the cage fouled on the concrete and prevented the alignment.
Back to Cheddar for angle grinders, generator and Alice;
then back to the dig. On went the generator, off came the
brackets and down came the rain. Once the cage frame had
been aligned, four wet lengths of scaff were clamped inside the
corners and a (wet) fabricated foot was fitted to the bottom of
each pole.
The next part of the game was to dig a hole under each foot to
allow a greater mass of concrete to be cast around them.
Task completed, we packed up soggily at 1445.
In the morning, Les and Tony continued breaking rocks and
raising the level of the foundations. Also dug a trench to the
shaft from the south west and inserted a 65mm plastic pipe, then
reburied it. This is intended to take the 'water main' (hosepipe)
under the cement to the shaft, also a convenient route for getting
cables, etc to the shaft.
In the afternoon, Alice arrived and, having broken and beaten
rock to Les' satisfaction, we started barrowing aggregate from the
heap to blind the surface ready for concreting.
In the evening, Tony cut four 15 inch (380mm) lengths of
scaffold and welded 'feet' on them. These are to form the
'stub' bases for the head frame, once cast into the concrete.
2010 (119) ~ Wed 14th Jul:
(1200-1630)
Les Oxborough
Les took a sledge hammer over to the dig and had a session of
rock bashing to add to and then to consolidate the foundation for
the concrete area round the shaft. He also drove in more
pegs to better define the required slope to ensure that the area
drains properly.
Les and Tony reconnected the ladder to its hanging belay,
but it is not yet fixed to the shaft.
Then removed the cage grill from the top of the shaft and
took various measurements to define the level of the concrete
collar, or possibly concrete apron, that will be cast round the
shaft. Whatever it is called it will have a slope so that
water will drain to the drain, cunningly placed so that it is at
the lowest point. Les produced a calculator and communed
with it for some time before announcing that all was well.
Having thus decided on the level and driven in pegs to celebrate
this, we started to backfill with rubble until repeated horsefly
attacks drove us away.
Les spent all day bricking up the drainage chamber and fixing
the iron picture frame on top. The top of this frame will
define the lowest point of the concrete 'collar' which will be cast
round the shaft.
Meanwhile, Tony laid more conveyor belting in the hut and
screwed three inch wide strips of ply to the inside of the hut to
cover the joints between the ply panels. Finished at
1615.
2010 (116) ~ Sat 10th Jul: (pm)
Les Oxborough
Les went over to the hole and laid a 4 in thick slab of concrete
to form the bottom of the drainage chamber.
2010 (114) ~ Fri 9th Jul: (0820-1630)
Alice Audsley, Tony Audsley
In the morning, Tony made up a 1ft by 9ins frame for the top of
the drainage chamber, a sort of iron picture frame is the best
description, lots of ill-fitting mitre joints and spotty welding.
Then 'finished' the second guard on the sheave wheel to
prevent the haulage cable from jumping out of the pulley groove on
the engine side of the wheel.
In the afternoon, Alice and Tony went over to the dig where they
dug under the yellow sump bucket and packed the space with gravel,
then raised the drainage pipe so that it was level with the sump
bucket outflow blue pipes. The whole pipe was then graded to
a suitable fall gradient and the trench backfilled.
Had enough of feeding the horseflies; went home.
2010 (113) ~ Thu 8th Jul: (0910 -
1630)
Alice Audsley, Les Oxborough, Tony Audsley
In the morning, Les went to Home Close and removed the formwork
from the top of the shaft and generally tidied the site.
Meanwhile at Cheddar, Tony worked on the sheave wheel, fitting
guides to prevent a slack cable from jumping out of the wheel
groove.
In the afternoon, Alice, Les and Tony worked on the site.
Firstly assembling the security grill atop the shaft. Then
later, aligning the drainage pipework and digging a hole hear the
shaft for a drainage chamber.
A long day (1000 - 1830 hrs) with not a great deal to show for
it. Working on the MOAB, increasing the torsional stiffness
and fixing a detachable sub-bracket on the top to support the
exhaust pipe. The pipe is wired to this to allow some degree
of horizontal movement (expansion). Fitted the exhaust pipe
and ran the engine to test it; seems OK. Tried the
'silencer' on the end, which makes a bit, but not much difference.
Refitted the guard to cover the pull start pulley and made
up a new stop to retain it in position as the MOAB interfered with
the old arrangement.
Doesn't seem much, but it took all day.
2010 (111) ~ Mon 5th Jul:
Tony Audsley.
Working on the winch in the morning, making up the 'Mother Of
All Brackets' to support the exhaust pipe. Because of
worries about stressing the very small studs holding the exhaust to
the cylinder block, this bracket was made as rigid and vibration
proof as possible.
After a lunch time session at Hunters', went over to the dig and
continued to work on the drainage trench. This was hindered
by the presence of two large blocks which did not want to come out
of the trench, a lot of words were exchanged before they were
persuaded to come out. Laid the drain-pipes roughly in
position and checked the slope - almost OK.
Over to the dig at 1000 hrs, removed the sacking from the top of
the shaft and found that the concrete was curing nicely.
Photographed it to make up for yesterday, then replaced the
sacking.
Started to remove the pile of half-bricks near the shaft in
preparation for digging a drainage trench, but came across a vole's
nest complete with pups. Replaced a few bricks around the
nest and left it. Shortly after, the mother started carrying
the pups out, taking them into the pile of whole bricks nearby.
We don't need to move these, so she should be OK there.
Spent the rest of the morning until 1300 hrs digging a drainage
trench from the shaft area to the drainage sump. Returned
from Hunters' at about 1415 hrs and did another hours worth of
deepening the trench before packing up for the day.
2010 (109) ~ Sat 3rd Jul:
Alice Audsley, Ian Gregory, Jeff Price, Les
Oxborough, Tony Audsley.
An imaginary Les Oxborough drilling holes in
the top of the cement ring
Alice bending the rebar
Slug tending the BBQ - a victim of passive
smoking
Alice, Slug, Jeff and Les ramming the mix into
the formwork.
This was quite an important day at the dig, which required the
remembering of all sorts of vital stuff. This was OK but I
forgot to take a camera! However, the technology exists to
provide you with imaginary (or 'virtual' as computer folk say),
images of the days events. These imaginary images also
download very quickly, so there is less stress on the
infrastructure of the web, but it does require a bit of effort on
your part. (Remember, you imagined it here first).
A full day (1000 - 1600 Hrs). Eight holes were drilled at
45° intervals round the top of the shaft. The top of the
shaft was then cleaned carefully using a Hoover 'Dustette' hand
vacuum cleaner, which used to belong to my Great Aunt Barbara.
Once all was spotless, the holes were fitted with short lengths
of 10mm rebar bent at 90°, these acted as support for a ring of
10mm rebar cunningly bent so that it fitted exactly and correctly
along the centreline of the concrete ring. Working to this
degree of precision makes one appreciate the difficulties they must
have had getting the Large Hadron Collider to a sufficient degree
of roundity.
The supports were resin bonded into the holes and the whole
assembly wired tightly together.
The BBQ was encouraged to light with some imaginary petrol
(don't try this with REAL petrol) and burgers and sausages were
produced for consumption at a very satisfactory stage of
carbonisation, while Slug vanished behind a vast cloud of
smoke.
After this, two and a half mixer loads of cement were produced
and rammed carefully home by all except Tony, who was attending to
the mixer and taking imaginary photographs. For those ardent
cement gricers and readers of 'Cement Weekly', the mix was 1:2:4,
cement sand and 14mm aggregate.
2010 (106,107) ~ Thu 1st Jul:
Les Oxborough (at Home Close), Tony Audsley (at
home!)
Les finished the formwork for the shaft, so fitting the
reinforcing, mixing and pouring is scheduled for this coming
Saturday - starting at 1000hrs.
At Cheddar, Tony found that the exhaust pipe leaked so rewelded
it, producing an incredibly ugly weld, which would not look out of
place on a Soviet railway locomotive.
Again, no one session deserves detailed description, but a lot
of work has gone on (some of it misdirected) and we are
approaching a stage where we can at last see the light at the
beginning of the tunnel. OK, it's perhaps not quite as
bad as that, but we are nearing the climax (?) of the surface
preparations.
Les has worked steadily at the site, preparing the formwork
and reinforcing for the extension to the top ring of the shaft.
Tony finished off the security grills and took them over
to the site, then (and this is the misdirected bit) started
making up a sheave wheel and framework to sit on top of the
headframe.
This was made up of bits of ex-MOD bed-frame, a wheel (from
Andrew Johnston), 25mm stainless bar (Les Oxborough), iron water
pipe (Wendy Roberts), bearings (found rusting and neglected
behind the Belfry) and, finally wodges of shim steel to make
everything fit together. The shim steel was BOUGHT (sorry)
many years ago from R.S. Components to align the engine of the
N.B. Mendip Digger with the stern gear and kept carefully ever
since just in case it might come in useful.
Also prepared some pulley devices, which will come into
prominence later, and cut off the top of an old aluminium beer
keg for use as a digging bucket.
2010 (096 - 099) ~ Tue 22nd - Fri
25th Jun:
At various times, AA, TA & Les Oxborough
Les Oxborough working on the shuttering on
the top of the shaft.
Les Oxborough has finally been dragged out of retirement; his
last known activity was the construction of the timber adit at
Longwood Valley Sink round about 1982/3 ish. Les has now
contracted to raise and level the top of the shaft by casting a
low reinforced concrete ring on top. Tony and Alice
unbolted the fixed ladder from the shaft, removed the topmost
section and hung the remaining ladder out of Les' way down
the centre of the shaft supported by a length of rebar.
NOTE: IT IS NOT SAFE TO USE THIS
LADDER.
It is usually best to keep well of of Les' way when he is
working, so Tony retired to Cheddar and finished off the grills,
then started work on a sheave wheel to go on top of the
headframe.
As well as this, the bank needed cutting back further to
allow the gate to open.
Then did the following in no particular order:-
Dug out more material from the bank and used it to fill the
'borrow pit'.
Tried anti-horsefly kit made from ScrewFix
disposable coverall and Bat Products
anti-mosquito headgear. This may well look rather quaint,
but it was cool to wear and very effective.
Worked on the winch, fitting the control levers, throttle
linkage and the main drive pulley.
Tested out Slug's stove by making and drinking five cups
of coffee. Found it to be entirely satisfactory.
Collected the yellow grills from Home Close and took them to
Cheddar. They are getting to be well travelled.
Made new hinges for the yellow grills and a latch and catch
to hold the gate in the open position.
Tried to interest Les Oxborough in the dig.
12JUN10: Tony digging in anti-horsefly
kit.
15JUN10: Preparing MK II hinges.
2010 (086) ~ Fri, 11th Jun (pm)
The Venus Figurine
Took the completed grills over to the dig. Dug out the
egg-shaped boulder that had been left by Wednesdays quartet.
Closer examination of one of their figures showed it to be
female, a veritable Venus figurine, so perhaps Wednesdays efforts
were partly directed to fertility rites. In which case,
considering the four individuals involved, I'm rather glad
that I wasn't.
2010 (084) ~ Wed, 9th Jun (Evening)
Bill Combley, Henry Bennett, Henry Dawson and Mark
Denning
Henry hasn't put in a report on this
evenings happenings - SO UNTIL HE DOES, I WILL MAKE SOMETHING
UP.
[Henry did put in a report, but I think that my version is
better than his, so it stays.]
Henry, Henry, Bill and Mark went over to the dig and frittered
away their time making little men out of concrete blocks and
bricks. One of the figures definitely started out as a man, but
by Friday afternoon two thirds of his manhood lay in ruins at his
feet - (Butcombe is believed to have this effect if consumed in
sufficient quantity).
It is possible that they also did some clearing round the top
of the shaft.
(At various times) Ben Selway, Jeff Price, Tony
Audsley, Vern Freeman.
AARGH - OH NO!!
It's The Winch Monster
A veritable crescendo of activity, most of it really rather
tedious, involving squares of conveyor belting (removed from the
bell-chamber of St Andrew's Church in 2000), ferrying of
concrete blocks, fiddling with security grills, more measuring of
levels around the shaft (plus a bit of trigonometry) and,
inevitably, the accursed winch, this time fitting grease nipples
so that the ball races will stand a chance of being lubricated
occasionally - hopefully, they will be grateful.
This is getting silly - it must be the
heat.
DO YOUR WORST
We will prevail !
2010 (076) ~ Sun, 30th May:
AM: Nick Winter, Stuart Lindsay, Tony Audsley.
Stu & Nick cleared the area round the shaft, while Tony dug
in the 'borrow pit' and spread clay inside the hut. Later
Stu and Nick did the digging and Tony just did the spreading.
PM: Alice Audsley, Chris Batstone, Ian
Gregory, Tony Audsley.
Alice, Chris & Ian continued digging and Tony continued
spreading and levelling. Eventually, the floor was pronounced
level and four pallets were dropped into position. Finished off
the day with a wittering session on the spoilheap.
The photograph shows Slug digging in the 'borrow pit',
supervised by Batspiss.
2010 (069) ~ Wed, 19th May
(I wouldn't normally put in this sort of thing in detail,
but considering the number of hours I have wasted on the ruddy
thing, here it is.)
Spent all of the morning reducing the level of Entropy in
'The Black Shed' at Cheddar, in order first to be able to
see, then later get to, the winch engine. Having got to
it, the carb was fitted with NEW bits and then given a severe
talking to, just in case that would help.
Now, the moment of truth - put in a little petrol and checked
for leaks; all seemed OK. I didn't think that the
engine was entirely to be trusted, so assembled a fire blanket
and two extinguishers just to be on the safe side.
Turned on the petrol, tickled the carb and pulled ......
ENGINE STARTED FIRST GO !!!!!!!!!!!!!!!!!!
It ran fairly steadily, seemingly rather rich and it will need
some fine adjustment, but WOW, not bad after years of standing
idle.
NOTE: If you are using an up-to-date
version of Firefox, Google
Chrome or Opera (v10.6), all of which
support HTML 5, then you will be able to hear
the musical tones of the engine by clicking on the control box
below. If you can't see the box, then you aint got it
and you are missing a treat. ( I believe that I.E. 9 might
manage it.)
2010 (066) ~ Sun, 16th May
Ian Gregory (Slug) Jeff Price, Chris Batstone,
Alice & Tony Audsley.
Alice and Tony fitted the wriggly tin roof. Slug, Jeff
and Chris broke up the last remaining boulder into satisfyingly
small bits.
The completed hut - well almost.
Jeff & Slug watch Chris attack the
boulder
The boulder hauled out of position
The remains of the boulder
2010 (065) ~ Sat, 15th May
Alice & Tony Audsley, Ian Gregory (Slug)
Took the hut door and cladding panels to the site and fitted
them into position.
Tangent [John Williams] visited and went down the shaft to
retrieve a carpenter's pencil that had been dropped.
2010 (064) ~ Fri, 14th May
... Before ...
Alice & Tony Audsley.
Took the framework of the hut over to t'hole. When
assembling the base framework we found that two of the concrete
block corner supports were considerably in the wrong place.
This must have been due to some sort of tectonic movements
because they had been measured incredibly carefully. After
some work with pick and shovel the offending corner supports were
re-sited and the hut framework erected.
... After ...
2010 (063) ~ Thu, 13th May
Alice & Tony Audsley
Dismantled the digging hut. Now ready to move it to the
dig.
2010 (059-062) ~ Mon, 10th - Fri,
12th May.
The Completed Digging Hut ...
Alice & Tony Audsley
At Cheddar, Alice & Tony installed an opening flap or
'window' in the front of the hut, fitted ship-lap
timbering over the rest of the front, then dowsed everything in a
mixture of creosote & bitumastic. The structure is now
complete and ready to be dismantled and transported to the
dig.
Jeff Price
Meanwhile, over at the dig on Tuesday evening, Jeff drilled ten
more holes in 'that' boulder.
Jeff drilled ten holes on Thursday, then another eight on
Friday evening.
2010 (053) ~ Mon, 3rd May AM/PM
Jeff drilling a boulder by the shaft; Slug
checking all is OK.
The boulder split and ready to be
removed.
GOT IT !
Jeff Price, Ian Gregory, Tony Audsley
Quote from Slug at the beginning of the session "I feel
like shit" - he looked like it too.
Another rock breaking session, drilling and hammering a gad
into the hole to break up the rocks that had been placed round
the shaft when the pit was backfilled in August 2008. At the end
of the morning, the Hilti battery was flat and the eastern
boulder was no more, so off to Hunters' for beer and battery
charging.
In the afternoon, the northern boulder was demolished and the
Hilti battery flattened again. This left the large red mudstone
block on the north side of the shaft, which had been supporting
one of the tripod legs. This was attacked with hammer and chisel
and a crack opened up across its whole width. After much furdling
and clearing round the boulder, the crack was opened sufficiently
to get a strop round the broken part of the boulder. The
intention was to use the Jeff's Land Rover winch to pull the
rock OUT, but on the first attempt the rock very nearly pulled
the Land Rover IN. On the second attempt the rock was hauled out
successfully and we smashed it up. Some more still to come
out.
Quote from Slug at the end of the day "I quite enjoyed
that" - which is strange because he still looked the
same.
Jeff worrying a boulder, (not posed, note the
flying stone dust)
Hauling out the boulder. E A S Y !
2010 (052) ~ Tue, 27th Apr (pm)
Jeff Price
Jeff went over to the dig in the afternoon with his 36V Hilti
and drilled 13 16mm holes up to 300mm long in the boulder between
the shaft and the stile. He then shook it to pieces with a sledge
hammer.
2010 (051) ~ Tue, 27th Apr (am/pm)
The digging hut foundations more or less
complete.
Alice & Tony Audsley.
More clay was needed to level the foundations, so we dug a
'borrow pit' near the centre of the depression and
barrowed clay from it to the hut foundations. Had lunch of quiche
and veg soup cooked over a Primus petrol stove.
A General view of the intended location of
the digging hut.
2010 (050) ~ Mon, 26th April (am)
Jeff Price, Tony Audsley.
A couple of hours spent moving all the remaining Caine Hill
clay and rock (except a few rocks which were sheltering a toad)
over to the hut foundations and continuing with the levelling
Jeff Price by the almost completed
foundation
2010 (049) ~ Sat, 24th April (pm)
Alice, Rosie & Tony Audsley.
Built up the hut foundations with rock and mud from Caine Hill
and built a temporary retaining wall on the south side.
Not a very tidy wall so hopefully it will soon be buried and out
of sight under our own spoil. Almost (but not quite)
reached the finished level.
Rosie & Alice Audsley emptying Caine Hill
spoil bags
2010 (048) ~ Mon 19th April
Ian Gregory (Slug), Tony Audsley
In the morning, TA and IG took a load of rocks and bags from
Caine Hill to t'hole. TA did the same in the
afternoon.
2010 (042-047) ~ March / April. (Summary of log
entries)
It's a bit tedious to go into things in minute detail but
eight loads of rock and mud ferried from Caine Hill to the dig,
some scrap steelwork was collected, a new magneto coil was bought
and fitted to the winch engine and the hut foundations were built
up slightly.
2010 (041) ~ Sat pm 6th March
Alice Audsley, Tony Audsley.
Spent a couple of hours levelling and building up the corner
concrete block supports for the base of the hut. Later AA
cleaned off bricks and TA barrowed rocks to build up the hut
foundations.
Foundations of the new engine/digging
hut.
2010 (022-040) February (Summary of log
entries)
Collected sheets of wriggly tin from Mole Valley
Farmers.
Took three Land Rover loads of bricks (thanks to Tony Norris)
from the farmhouse to the dig.
Took one load of Caine Hill rock to t'hole.
Did more work on the 'flat-pack' digging hut.
Spent a day at the dig cleaning up bricks.
Started (again!) working on the motorised winch.
12FEB10: The 'Flat Pack' digging
hut
2010 (003-021) ~ January (Summary of log
entries)
The rest of January involved a lot of rather boring surface
preparation, this was too tedious to record in detail, some
'highlights' were:-
Started work (at home) on constructing a portable digging hut
/ engine house / cement store.
Collected 12 old bunks - useful for their heavy-gauge angle
iron.
Made up a telephone system for the dig.
Played in the snow.
Sunday Afternoon 3rd January
(2010.002)
Continued shifting rocks for the foundation, then sorted
through the timber pile and selected some pieces suitable for the
framework of the hut. Took these back to Cheddar.
2010 (001) ~ Sat, 2nd Jan (pm)
Jeff Price, Tony Audsley
Working on the foundations of the new digging hut using rock
from Caine Hill, building up a level area about 8ft square.